- Identify and calculate project costs including materials, physical resources, and personnel
- Select and allocate resources to create accurate cost estimates
- Determine project affordability and viability
- Assess long-term impact on company operations
- Create comprehensive resource and cost plans
Cost Planning for Task 1 Exam
For the ESP exam, you'll create cost plans with no overhead costs. Focus on direct personnel costs, hardware/infrastructure costs, and calculating profitability over 3 years.
Key Cost Categories
- Personnel Costs: Staff hourly rates × hours worked
- Hardware/Infrastructure: One-time purchases and upgrades
- Annual Running Costs: Ongoing operational expenses
- Revenue Projections: Current and future revenue with/without solution
Table 1: Individual Resource Costs
Create a separate table for EACH staff member showing their tasks, hours, and costs.
Example: Sarah Chen (Senior Software Engineer)
| Task | Hours | Cost |
|---|---|---|
| Develop Module 1: Stock and Inventory Management | 50 | £4,250 |
| Integration Testing | 6 | £510 |
| Total Cost | £4,760 | |
Repeat this table for each resource: James Wilson (Junior Software Engineer), Marcus Thompson (Hardware and Networking Technician), Priya Patel (Cloud Systems Architect), Project Lead
Table 2: Total Project Costs
This table includes ALL costs: staff totals, hardware, infrastructure, and other one-time expenses.
| Task | Cost |
|---|---|
| Sarah Chen (Senior Software Engineer) - Total | £4,760 |
| James Wilson (Junior Software Engineer) - Total | £2,100 |
| Marcus Thompson (Hardware and Networking Technician) - Total | £5,600 |
| Priya Patel (Cloud Systems Architect) - Total | £3,750 |
| Project Lead - Total | £7,400 |
| Purchasing of Hardware | £15,300 |
| Upgrades to Company Infrastructure | £9,800 |
| Software Development Company Base Fee | £18,000 |
| Cloud Server (Option 2) | £462 |
| Training T-Learn Automotives Staff | £1,200 |
| Total Cost of Solution | £68,372 |
Table 3: Annual Running Costs
Ongoing costs that occur every year after the solution is implemented.
| Task | Cost |
|---|---|
| Web Hosting and Online Advertising | £3,600 |
| IT Support Technician | £33,000 |
| Total Annual Running Costs | £36,600 |
Note: This cost repeats every year (multiply by 3 for 3-year total)
Table 4: Revenue Projections
Calculate total revenue over 3 years with and without the solution. Increases are cumulative (added to previous year).
| Year | Revenue WITHOUT Solution | Revenue WITH Solution |
|---|---|---|
| Current (Year 0) | £1,574,985 | £1,574,985 |
| Year 1 | £1,574,985 | £1,771,858 (+12.5%) |
| Year 2 | £1,574,985 | £2,002,200 (+13%) |
| Year 3 | £1,574,985 | £2,302,530 (+15%) |
| Total (3 years) | £4,724,955 | £6,076,588 |
| Total Additional Revenue (3 years) | £1,351,633 | |
Table 5: Total Profit After 3 Years
Final profitability calculation showing if the solution is financially viable.
| Item | Amount |
|---|---|
| Total Additional Revenue (3 years) | £1,351,633 |
| Cost of Solution | -£68,372 |
| Annual Running Costs × 3 years | -£109,800 |
| Total Profit After 3 Years | £1,173,461 |
Interpretation: A positive profit indicates the solution is financially viable. If negative, the solution costs more than it generates.
Key Tips for Cost Planning
Common Mistakes to Avoid
- ❌ Forgetting to include Project Lead costs in Table 2
- ❌ Not multiplying annual running costs by 3 for the 3-year period
- ❌ Calculating revenue increases from the original amount instead of cumulative
- ❌ Forgetting to subtract costs from revenue in the profit calculation
- ❌ Including overhead costs (the brief states there are none)
Calculation Checklist
- Create individual resource tables with hours × hourly rate
- Sum all staff totals + hardware/infrastructure costs
- List annual running costs (these repeat each year)
- Calculate cumulative revenue increases year-on-year
- Final profit = Additional Revenue - Solution Cost - (Running Costs × 3)