Task 1 · Gantt Charts
up to +100 XP
Stop 1.1 · Task 1 · 5 min

Gantt Charts

Master project scheduling and task management with Gantt charts

Learning Objectives:
  • Understand the purpose and structure of Gantt charts
  • Learn to assess team strengths and assign appropriate tasks
  • Master scheduling decisions based on deadlines
  • Apply task prioritisation based on requirements analysis
  • Demonstrate proper resource allocation to project tasks
  • Use appropriate software development lifecycles

What is a Gantt Chart?

A Gantt chart is a visual project management tool that displays tasks, their durations, and dependencies over time. It shows when tasks should start and finish, helping teams coordinate work and meet deadlines effectively.

Key Components of Gantt Charts

Assessing Team Strengths and Task Assignment

Effective project planning requires understanding team member capabilities and matching them to appropriate tasks.

Steps for Team Assessment

  1. Skills Inventory: Document each team member's technical and soft skills
  2. Experience Analysis: Consider previous project experience and domain knowledge
  3. Availability Assessment: Determine each person's capacity and schedule constraints
  4. Workload Balancing: Distribute tasks to prevent overloading individuals
  5. Growth Opportunities: Assign tasks that develop team members' skills

Task Assignment Principles

Making Scheduling Decisions

Effective scheduling requires balancing project constraints, resource availability, and quality requirements.

Scheduling Considerations

Deadline Management Strategies

  1. Break down large tasks into smaller, manageable chunks
  2. Identify tasks that can be done in parallel
  3. Prioritise critical path activities
  4. Build in review and testing time
  5. Plan for iterative development cycles

Resource Allocation

Proper resource allocation ensures project tasks have the necessary people, tools, and materials to be completed successfully.

Types of Resources

Resource Allocation Best Practices

Software Development Lifecycles

Choosing the right SDLC model helps organise project tasks efficiently and improves delivery success.

Common SDLC Models

Choosing the Right SDLC

Gantt Chart Best Practices

Key Tips for Task 1 Exam

Critical Gantt Chart Rules

Task Dependencies Example

Correct order for Module 1:

  1. Develop Module 1 (50 hours)
  2. Create test plan for Module 1 (2 hours)
  3. Unit testing for Module 1 (8 hours)
  4. Fix minor faults (4 × 5 hours = 20 hours)
  5. Integration testing (only after Module 2 is also developed)
  6. Deploy Module 1 (7 hours)

Common Mistakes to Avoid

Resource Assignment Tips

Meeting the 8-Week Deadline

Quick check · 10 questions

Check what stuck.

+10 XP each
Question 1

Question 1 of 10

How many modules are needed BEFORE you can do integration testing?

Question 2

Question 2 of 10

When should unit testing be scheduled for a module?

Question 3

Question 3 of 10

What must be created BEFORE starting unit or integration testing?

Question 4

Question 4 of 10

When should modules be deployed?

Question 5

Question 5 of 10

When should infrastructure be upgraded?

Question 6

Question 6 of 10

When should the back-end database be developed?

Question 7

Question 7 of 10

What should you always include in your Gantt chart for unexpected issues?

Question 8

Question 8 of 10

What is a common mistake when assigning tasks?

Question 9

Question 9 of 10

Who should be assigned to complex, critical modules?

Question 10

Question 10 of 10

What is a common mistake when scheduling integration testing?