Business Context · Technical Change Management
up to +100 XP
Stop 5.4 · Business Context · 3 min

Technical Change Management

Learn to manage technological and organizational changes

Learning Objectives:
  • Understand internal and external factors triggering change
  • Describe how organisations respond to change
  • Explain the change management process
  • Evaluate the feasibility and risks of digital projects

Technical Change Management

Technical Change Management focuses on how organisations plan, implement, and manage technological or structural changes to maintain stability and improve performance. It ensures changes are introduced smoothly, efficiently, and with minimal disruption to operations.

Internal Factors Triggering Change

Internal factors originate within the organisation and often require adaptation to maintain performance and growth.

External Factors Triggering Change

External factors come from the organisation's outside environment and can influence its strategy, operations, or technology.

How Organisations Can Respond to Change

Organisations can respond to change by updating policies, processes, systems, and structures to stay competitive and compliant.

Change Management Process

The change management process ensures that any technical or organisational change is planned, reviewed, implemented, and monitored effectively.

  1. Identify type of change – new system or amendment
  2. Change Advisory Board (CAB) role: prioritise requests, approve stages, monitor progress, and provide feedback
  3. Identify changes to be made – use SMARTER objectives (Specific, Measurable, Achievable, Realistic, Time-bound, Evaluated, Reviewed)
  4. Identify impact of change – assess positive and negative effects
  5. Allocate resources – budget, time, staff, and technology
  6. Communicate risks and impacts – gain stakeholder acceptance
  7. Configure new systems/processes – integrate with legacy systems
  8. Testing – use reproducible and controlled environments
  9. Implement change – parallel, phased, direct, or pilot approach
  10. Document process – record requirements, training manuals, and decisions
  11. Rollback planning – establish backups and recovery plans
  12. Training needs – organise new or refresher sessions
  13. Monitor progress – post-implementation review and feedback
  14. Version control – track all system updates and revisions

Factors Determining Feasibility of a Digital Project

Benefits

Drawbacks

Risks of Project Failure or Disruption

Constraints Limiting Successful Project Implementation

Quick check · 13 questions · up to 100 XP

Check what stuck.

+10 XP each
Question 1

Question 1 of 13

Which is an internal factor that triggers change?

Question 2

Question 2 of 13

Which is an external technological factor that triggers change?

Question 3

Question 3 of 13

What does CAB stand for?

Question 4

Question 4 of 13

Which is a role of the CAB?

Question 5

Question 5 of 13

What does the extra "E" and "R" add to SMART in SMARTER objectives?

Question 6

Question 6 of 13

Running the old and new systems side by side for a time is which method of implementing change?

Question 7

Question 7 of 13

Switching off the old system and starting the new one immediately is…

Question 8

Question 8 of 13

Trying the new system with one branch before rolling it out is…

Question 9

Question 9 of 13

Why is rollback planning important?

Question 10

Question 10 of 13

Which is a risk that affects whether a digital project is feasible?

Question 11

Question 11 of 13

Which is a constraint on a digital project?

Question 12

Question 12 of 13 · Match the pairs

Match each method of implementing change to its description.

Parallel
Phased
Direct
Pilot
Question 13

Question 13 of 13 · Fill in the blanks

Change requests are prioritised and reviewed by the change board.